NEW QUESTION 126
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
What will be the impact on the benefits?
- A. An additional cost of (GBP)1.5m to deliver the services provided by the Facilities Division.
- B. Reduced savings, now (GBP)10m over 10 years.
- C. Outsourcing project cost reduced by 50%.
- D. Increased savings of (GBP)5m over 10 years from the new initiative to centralize the services provided by the Facilities Division.
Answer: B
Explanation:
Topic 8, Progress Theme
NEW QUESTION 127
Which principle is central to the quality theme and provides explicit understanding of what the project will create?
- A. Manage by exception
- B. Focus on products
- C. Manage by stages
- D. Learn from experience
Answer: B
NEW QUESTION 128
MANAGING A STAGE BOUNDARY
The ABC Company trainers have been accredited and the course booking procedures have been amended.
The 'managing a stage boundary' process is taking place at the end of stage 3.
Which activity should occur during the 'update the business case' activity?
- A. Update the overall plan with the time and cost taken to develop the 'e-learning course' and 'amended course booking procedures'
- B. Review whether the possible sales of the training course to external companies are likely to cover the project costs.
- C. Break the 'planned pilot courses' down into component products in order to identify the work required to deliver them.
- D. Review whether a new team manager should be appointed to lead the delivery of the pilot courses during stage 4.
Answer: A
NEW QUESTION 129
Who would be responsible for maintaining the Configuration Item Records?
- A. Project Assurance
- B. Project Support
- C. Project Manager
- D. Team Manager
Answer: B
Explanation:
Explanation/Reference:
Progress Theme
Testlet 1
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
* Design for each month - correctly showing at public holidays and new company logo
* Selected photographs- 12 professionally-produced photographs, showing different members of staff
* Selected paper and selected envelope - for printing and mailing the calendar
* Chosen label design - a competition to design a label will be held as part of this project
* List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
* Create the customer fast using information from the Accounts and Marketing departments
* Confirm compliance with the Data Protection Legislation
* Create a design for each month - this will be done by the internal creative team
* Select and appoint a professional photographer
* Gather photograph design ideas from previous project and agree photographic session schedule
* Prepare a production cost forecast
* Select paper and envelope.
Stage 3 will include the activities to:
* Produce and select tie professionally-taken photographs
* Hold the label design competition and choose the label design
* Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be E20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +E6,000 / -E6,000. A change budget of E500 has been allocated but there is no risk budget.
NEW QUESTION 130
The 'classroom-based training materials' will be used as the basis for developing the 'e-learning course'. As a
result, the executive wants to ensure that the 'classroom-based training materials' are of the required standard.
The executive has asked to meet the project manager every day during stage 2 to discuss progress and
identify any concerns regarding quality.
Is this an appropriate approach to applying the organization theme, and why?
- A. No, because the senior user should be responsible for specifying the quality criteria for the training
materials. - B. No, because the project manager should be given authority to manage the project on a day-to-day basis.
- C. Yes, because the executive should be available to provide ad hoc direction to the project manager.
- D. Yes, because the executive should be the key decision-maker on the project, supported by other project
board members.
Answer: B
NEW QUESTION 131
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost (GBP)2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of (GBP)20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?
- A. Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.
- B. The total expected savings over 10 years, at current prices, is (GBP)20m.
- C. The 10-year outsourcing contract, at current prices, will be worth (GBP)80m.
- D. The confirmed cost of the Outsourcing project is (GBP)2.5m, but with considerable savings over 10 years.
- E. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.
Answer: B,E
Explanation:
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php
NEW QUESTION 132
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the 'e-learning course' has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.
Is the team manager's response appropriate, and why?
- A. No, because the project manager needs detailed plans to manage the work of several teams.
- B. Yes, because team plans are mandatory on a project of this size and complexity.
- C. No, because the team plan must be submitted to project assurance to check it is viable.
- D. Yes, because a supplier may want to keep the details of the specialist work confidential.
Answer: A
NEW QUESTION 133
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Stakeholder analysis: Interested parties section?
- A. Delete entry 11 because the photographer is internal to the project management team.
- B. Delete entry 12 because the printing of the calendars is outside of the scope
- C. Add 'Internal Creative Team'.
Answer: C
NEW QUESTION 134
It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?
- A. Follow-on action recommendations
- B. Risk Register
- C. Lessons Report
- D. Project closure notification
Answer: C
NEW QUESTION 135
Which of the following statements describes an outcome?
- A. Any of the projects specialist products
- B. A measurable improvement resulting from a change
- C. Something perceived as advantages by a stakeholder
- D. A result of the change derived from using the project's products
Answer: D
NEW QUESTION 136
ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.
Is this an appropriate application of the 'tailor to suit the project' principle, and why?
- A. Yes, because the standard course development structure should be tailored to suit the project.
- B. No, because a simple project should have no more than two management stages.
- C. No, because the standard course development structure should be applied to the project.
- D. Yes, because the project manager can adapt or combine PRINCE2 process to suit the project.
Answer: A
NEW QUESTION 137
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff.
This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Risk management procedure heading?
- A. Every threat and opportunity identified must be clearly defined in terms of cause, event and effect.
- B. Probability will be assessed against the scales defined in this Risk Management Strategy.
- C. 'Reduce' Response actions which result in a lower impact and/or probability rating.
- D. Any risk which has an expected value of more than £1 k will NOT be registered.
- E. When a new problem arises, a full impact analysis will be undertaken to assess the impact on the project' objectives and Business Case.
Answer: A,B
NEW QUESTION 138
Which of the following statements best describes what a risk owner is?
- A. Carry out the response actions to a risk
- B. Best placed to keep an eye on the risk
- C. Reports to the project manager regularly on the status of a risk
- D. Responsible for management, monitoring and control of all aspects of a risk
Answer: D
NEW QUESTION 139
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?
- A. Yes, because a team plan to gain accreditation of the 'e-learning course' is required to be part of the work package.
- B. No, because the work package should be checked to confirm the reporting arrangements of the
'e-learning course'. - C. No, because it is the configuration item record of the relevant product description that is updated, not the work package.
- D. Yes, because the project manager needs to receive confirmation that work has been completed and approved.
Answer: D
NEW QUESTION 140
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
What statement applies to the Records section?
- A. Move entry 6 to the Configuration Management Strategy because it defines the identification scheme for
the project's products. - B. Move entry 7 to Communication procedure because it refers to the method to be used for communication to
external parties. - C. Move entry 8 to Tools and techniques because it refers to a filing technique.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION 141
Which of the following statements would NOT be included in the Project Product Description?
- A. Quality criteria
- B. Composition
- C. Project level tolerances
- D. Purpose of the product
Answer: A
NEW QUESTION 142
HOTSPOT
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.
Using the additional Information provided for this question In the Scenario Booklet, answer the following question.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Answer:
Explanation:
NEW QUESTION 143
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
* Design for each month - correctly showing at public holidays and new company logo
* Selected photographs- 12 professionally-produced photographs, showing different members of staff
* Selected paper and selected envelope - for printing and mailing the calendar
* Chosen label design - a competition to design a label will be held as part of this project
* List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
* Create the customer fast using information from the Accounts and Marketing departments
* Confirm compliance with the Data Protection Legislation
* Create a design for each month - this will be done by the internal creative team
* Select and appoint a professional photographer
* Gather photograph design ideas from previous project and agree photographic session schedule
* Prepare a production cost forecast
* Select paper and envelope.
Stage 3 will include the activities to:
* Produce and select tie professionally-taken photographs
* Hold the label design competition and choose the label design
* Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
The team member collating the list of customers has now forecast that it will NOT be complete by the end of this stage as originally planned, due to a number of new prospective customers' details not yet being available.
What action should the team member take?
- A. Report the forecast delay in the next Checkpoint Report to the Executive.
- B. Raise an issue to inform the Project Manager.
- C. Make an entry in the Risk Register so the Project Manager can decide on appropriate action.
- D. Add the product to the next Stage Plan in order to allocate additional resources and complete the work.
Answer: B
NEW QUESTION 144
Which 2 statements should be recorded under the Expected benefits heading?
- A. The calendar will contain photos of both staff and company products.
- B. The Marketing department want a very high quality, glossy product as they believe this will be more appealing to customers.
- C. Increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months.
- D. It will be similar to calendars sent out in previous years
- E. The Marketing department believes that the benefits of a good company image, as portrayed by a successful calendar, will last into a second year and bring the same increase in orders.
Answer: C,E
NEW QUESTION 145
The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?
- A. Include the tolerances for the work package 'delivered pilot courses' in the project plan.
- B. Ensure that the team manager for the work package 'delivered pilot courses' is included as a resource.
- C. Update the project's business case to show any new key risks that have been identified.
- D. Include the actual time and cost of the work to prepare the 'marketing materials' in the project plan.
Answer: D
Explanation:
Explanation/Reference: https://www.prince2primer.com/prince2-2017-update-project-plan-business-case/
NEW QUESTION 146
Which of the following risk responses can be used for either an opportunity or a threat?
- A. Reduce
- B. Share
- C. Enhance
- D. Reject
Answer: B
NEW QUESTION 147
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Stakeholder analysis: Interested parties section?
- A. Delete entry 11 because the photographer is internal to the project management team.
- B. Delete entry 12 because the printing of the calendars is outside of the scope
- C. Add 'Internal Creative Team'.
Answer: C
NEW QUESTION 148
Which of the following activities is the Executive responsible for?
- A. Responsible for the Benefits Review Plan post project
- B. Ensure the desired outcome of the project is specified
- C. Assess and update the Business Case at the end of each stage
- D. Responsible for the benefits review plan
Answer: D
Explanation:
Explanation/Reference:
Organization Theme
Testlet 1
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured
his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall
perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a
publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing
project. She has the authority to commit the annual business marketing budget, from which the project will be
funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar,
in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still
as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature
in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now
maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment
needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a
history of successful work. This company has been selected to take the photos for the company calendar. It
has yet be decided which of the photographers to use.
NEW QUESTION 149
Which 2 alternative actions apply to the proposed user assurance for this project?
- A. Retain because they are both very positive about outsourcing the selected business functions.
- B. Retain because their divisions will be the major users of the outsourced services and they can provide the
user perspective on the impact of any proposed changes. - C. Retain because they are able to help identify stakeholders and their communication requirements.
- D. Retain because selecting only one of them may cause unnecessary conflict.
- E. Remove because neither of these individuals are from the business functions to be outsourced.
Answer: B,C
Explanation:
Explanation/Reference:
Organization Theme
Question Set 3
NEW QUESTION 150
......
New PRINCE2 PRINCE2-Practitioner Dumps & Questions: https://www.vceengine.com/PRINCE2-Practitioner-vce-test-engine.html
Dumps to Pass your PRINCE2-Practitioner Exam with 100% Real Questions and Answers: https://drive.google.com/open?id=1_3bzIHH8E3W-6pTA49X6tnIfvBfB8cEh