NEW QUESTION 49
A driving relationship is _____________________.
- A. A finish-to-start relationship.
- B. A critical relationship.
- C. The link between two related activities.
- D. The link between a predecessor and the activity whose dates it controls.
Answer: D
NEW QUESTION 50
The activity with the most total float is:
- A. Activity D.
- B. Activity I.
- C. Activity C.
- D. Activity F.
Answer: B
NEW QUESTION 51
What activities are concurrent to Activity 2001 in the "normal" schedule?
- A. 1000.
- B. 1001.
- C. 7001.
- D. 2003.
Answer: C
NEW QUESTION 52
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 10 days.
- B. 0 days.
- C. 5 days.
- D. 15 days.
Answer: B
NEW QUESTION 53
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
- A. Use the forward-looking critical path of the most current updates.
- B. Use the progressed portion of the critical path of the baseline schedule.
- C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
- D. Use the progressed portion of the critical path of all the updates previous to the current update.
Answer: A
NEW QUESTION 54
Each of the following accurately describes total float in a schedule EXCEPT:
- A. Can be positive or negative.
- B. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
- C. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.
- D. The amount of time an activity can be delayed without delaying the overall project completion time.
Answer: B
NEW QUESTION 55
How much Total Float does drafting the product manual have?
- A. 5 workdays.
- B. 0 workdays.
- C. 10 workdays.
- D. 15 workdays.
Answer: C
NEW QUESTION 56
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Front end loading.
- B. Multiple calendars.
- C. Preferential logic.
- D. Start and finish constraints.
Answer: A
NEW QUESTION 57
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
- A. 12.
- B. 14.
- C. 13.
- D. Cannot be determined.
Answer: A
NEW QUESTION 58
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 300 lifts
- B. 150 lifts
- C. 45 lifts
- D. 450 lifts
Answer: D
NEW QUESTION 59
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
- A. 03-21-04
- B. 03-11-04
- C. 02-19-04
- D. 03-20-04
Answer: B
NEW QUESTION 60
Which of the following project planning situations is the most frequent contributor to cost overruns?
- A. Inappropriate definition of work breakdown structure
- B. Inadequate definition of scope at the estimate (budget) stage
- C. lack of detailed planning for operational start-up
- D. Insufficient planning for change management
Answer: B
NEW QUESTION 61
Which of the following is NOT true?
- A. Constraints can interfere with the longest path calculation.
- B. A network must contain only one Critical Path.
- C. Multiple calendars can affect the total float calculation.
- D. Remaining durations can exceed original durations.
Answer: D
NEW QUESTION 62
Time-scaled logic diagrams are
- A. Logic networks that are drawn to match the calendar.
- B. Used to calculate the most probable activity duration.
- C. Only calculated using a computer.
- D. The same as a pure-logic diagram.
Answer: A
NEW QUESTION 63
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 2003 and 7001.
- B. 4001, 5001 and 6001.
- C. 4001 and 5001.
- D. 2004.
Answer: C
NEW QUESTION 64
At the end of month one, did the delay to the parking structure foundation delay the project?
- A. Yes, by 14 calendar days.
- B. Yes, by 4 calendar days.
- C. NO.
- D. Yes, by 9 calendar days.
Answer: B
NEW QUESTION 65
Why does activity 11001 not show successor activities?
- A. It is the penultimate work required for the project
- B. The early finish and late finish are circular
- C. The scheduler forgot to add the successor activities
- D. It is the final activity for the required work for the project
Answer: D
NEW QUESTION 66
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 20 months.
- B. 22 months.
- C. 21 months.
- D. 19 months.
Answer: A
NEW QUESTION 67
Which statement is true?
- A. Where compensability can be established, excusability is assumed.
- B. Where compensability can be established, excusabltity cannot be assumed.
- C. Where compensability cannot be established, excusability is assumed.
- D. Where compensability cannot be established, excusability is a given.
Answer: C
NEW QUESTION 68
What problems can a soils engineer deal with on a project?
- A. Survey error.
- B. Archeological findings.
- C. Hidden subsurface conditions.
- D. Toxic soils.
Answer: C
NEW QUESTION 69
Identify the minimum project duration.
- A. 20 months.
- B. 21 months.
- C. 16 months.
- D. 19 months.
Answer: A
NEW QUESTION 70
What is the free float for Activity F?
- A. 0months.
- B. 1months.
- C. 3 months.
- D. 2month.
Answer: A