[Feb 11, 2024] C_S4PPM_2021 Test Engine files, C_S4PPM_2021 Dumps PDF
Latest SAP C_S4PPM_2021 PDF and Dumps (2024) Free Exam Questions Answers
SAP C_S4PPM_2021 exam is designed to test the knowledge and skills of individuals in the area of SAP S/4HANA Portfolio and Project Management. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification is intended for consultants, project managers, and other professionals who are involved in the implementation and management of SAP S/4HANA solutions. C_S4PPM_2021 exam covers a range of topics, including project planning, project execution, project monitoring and controlling, and project closeout.
SAP C-S4PPM-2021 certification exam consists of 80 questions and has a time limit of 180 minutes. C_S4PPM_2021 exam is available in English and is conducted online. The passing score for C_S4PPM_2021 exam is 65%. C_S4PPM_2021 exam fee for this certification is $550.
NEW QUESTION # 49
What must you do before you can use multiple currencies in financial planning in portfolio management?
- A. Define a subnet of currencies in portfolio and project management
- B. Define a subnet of currencies in project system
- C. Select multiple currencies in the portfolio definition
- D. Select multiple currencies in the portfolio item
Answer: B
NEW QUESTION # 50
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?
- A. Role assignment and staffing
- B. Staffing by authorization
- C. Qualification determination
- D. Extended staffing
Answer: D
NEW QUESTION # 51
When are decision points for portfolio items created?
- A. After planning of financial values of an item
- B. During master date maintenance of an item
- C. During creation of an item
- D. After approval of an item
Answer: C
NEW QUESTION # 52
Which cost planning process can you use at item level?
NOTE: There are 2 correct answers to this question.
- A. Integrated cost planning
- B. Hierarchical cost planning
- C. Rollup of cost planning
- D. Manual cost planning
Answer: A,D
NEW QUESTION # 53
One of the tasks of your project has subtasks. You wants to restrict time recording to the subtasks.
How can you achieve this in customizing?
- A. Deactivate the mirrored task indicator for the project type
- B. Deactivate time recording for tasks
- C. Activate task hierarchies with summarization
- D. Activate task hierarchies without summarization
Answer: D
NEW QUESTION # 54
What data can you synchronize between a portfolio item and an initiative using Decision Flow management?
- A. Development Cost
- B. Documents
- C. Metrics
- D. Notes
Answer: A
NEW QUESTION # 55
What is the priority field in the project definition of a project management project used for?
- A. To determine the scheduled dates for the project
- B. To determine the approval authorizations required
- C. To restrict the selection of project types
- D. To support the evaluation of projects
Answer: D
NEW QUESTION # 56
You want to use a customer-specific status for items.
How do you configure the status in customizing?
- A. Create the status and status transition within the portfolio type
Assign the portfolio item type to the portfolio type - B. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
- C. Create a status profile for the portfolio item objet type
Create the status within the status profile
Assign the status profile to a portfolio item type - D. Create the status
Assign the status to a portfolio item type
Specify the status transitions with respect the portfolio item type
Answer: D
NEW QUESTION # 57
How can an existing project management project be integrated with SAP controlling?
NOTE: There are 2 correct answers to this question.
- A. Assign the project roles to an existing internal order manually
- B. Transfer the project structure element internal orders
- C. Transfer the project structure element to project system (PS)
- D. Assign the project definition to an existing PS project definition manually
Answer: A,D
NEW QUESTION # 58
What do you use the check Conflict button for?
NOTE: There are 3 correct answers to this question
- A. Adjustment of work according to resource availability
- B. Adjustment of dates of staffing
- C. Adjustment of dates of roles
- D. Adjustment of distribution of staffing
- E. Adjustment of work according to roles assignment of a task
Answer: B,C,D
NEW QUESTION # 59
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
- A. The edit in parallel indicator is inactive for the role type in customizing
- B. The flexible Assignment indicator is active for the rile type in customizing
- C. The role demand for the timeframe is too low
- D. The assigned effort for either of the resource assigned is to high
Answer: A
NEW QUESTION # 60
A WBS element has been created automatically for a project management project. A change is made to the organizational unit of the project definition.
When is the master data of the internal order updated with the change?
- A. Upon the next transfer
- B. Upon release of the WBS element
- C. Upon the next cost planning run
- D. Upon release of the project
Answer: A
NEW QUESTION # 61
Where can you define the scheduling type?
NOTE: There are 3 correct answers to this question.
- A. On task level
- B. ON phase level
- C. In customizing
- D. On project definition level
Answer: C,D
NEW QUESTION # 62
Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.
- A. Organizational units
- B. plants
- C. Qualifications
- D. Work centers
Answer: A,C
NEW QUESTION # 63
What is the PR/PLAN_INI_PREP report used for?
- A. To create financial and capacity categories and groups based on customizing
- B. To transfer recoded time from CATS to PPM
- C. To upload financial data from Microsoft Excel
- D. To transfer costs from accounting objects to PPM
Answer: A
NEW QUESTION # 64
Which of the following can be viewed in the item dashboard?
NOTE: There are 3 correct answers to this question.
- A. Standard fields
- B. Documents
- C. metrics
- D. authorizations
- E. Custom fields
Answer: A,C,E
NEW QUESTION # 65
You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question
- A. Update the capacity requirements from the roll-up of task requirements
- B. Use a distribution function
- C. Enter the vales manually
- D. Apply a distribution rule
- E. Copy values from resource assignments
Answer: A,B,C
NEW QUESTION # 66
......