C_S4PPM_2021 Exam Practice Questions prepared by SAP Professionals


The SAP C_S4PPM_2021 certification exam consists of 80 multiple-choice questions that need to be answered within a time limit of 180 minutes. The exam is available in English and can be taken at any SAP authorized testing center. To apply for this certification exam, candidates must possess basic knowledge of SAP S/4HANA Portfolio and Project Management and have at least six months of practical experience in implementing and using the software. The certification exam is ideal for professionals who are seeking to improve their skills in portfolio and project management using SAP S/4HANA software and are looking to advance their careers in this field.


The SAP C-S4PPM-2021 Certification Exam is an industry-recognized certification that validates the skills and knowledge of individuals in the field of portfolio and project management. This certification is designed for professionals who work with SAP S/4HANA Portfolio and Project Management solutions and want to demonstrate their expertise in this area.

 

NEW QUESTION # 25
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?

  • A. Enter an actual finish date of the task in the future
  • B. Set the task status to in process
  • C. Confirm the task using a completion percentage of less than 100
  • D. Ensure that the Rem. Work manually indicator is inactive

Answer: D


NEW QUESTION # 26
Decision Flow management is delivered with standard scenarios.
For which combination of object types can you define a standard attitude synchronization?

  • A. Decision point and WBS element
  • B. Portfolio item and WBS element
  • C. Decision point and activity milestone
  • D. Decision point and PS project definition

Answer: A


NEW QUESTION # 27
Which of the following multi-currency scenario are supported?
NOTE: There are 2 correct answers to this question

  • A. Items In a bucket an only use bucket currencies
  • B. Item currency can be inherited from the assigned bucket
  • C. Multiple planning currencies can be used in one bucket
  • D. Bucket in a portfolio can use different currencies

Answer: B,D


NEW QUESTION # 28
You have defined an item template. When you create a new item, you notice that you cannot select the template.
What could be the reason for this?
NOTE: There are 2 correct answers to this question

  • A. The item template start date is in the future
  • B. The item template has the Activate status
  • C. The item template is not available in the selected bucket
  • D. The item template has a different item type

Answer: C,D


NEW QUESTION # 29
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?

  • A. The edit in parallel indicator is inactive for the role type in customizing
  • B. The assigned effort for either of the resource assigned is to high
  • C. The role demand for the timeframe is too low
  • D. The flexible Assignment indicator is active for the rile type in customizing

Answer: A


NEW QUESTION # 30
No upcoming milestone are shown in the my projects SAP Fiori app.
What are the reasons for this?
NOTE: There are 2 correct answers to this question

  • A. You are not defined as the project Responsible
  • B. Milestone is not identified as critical
  • C. Milestone is not identified as mandatory
  • D. Project is not released

Answer: A,D


NEW QUESTION # 31
What can you define in the item template?

  • A. Category
  • B. Financial planning
  • C. Link to a project management project
  • D. Sequence of decision points

Answer: A


NEW QUESTION # 32
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question

  • A. Project management projects
  • B. Standalone items
  • C. Project system project
  • D. Initiatives

Answer: B,D


NEW QUESTION # 33
Which cost planning process can you use at item level?
NOTE: There are 2 correct answers to this question.

  • A. Manual cost planning
  • B. Hierarchical cost planning
  • C. Rollup of cost planning
  • D. Integrated cost planning

Answer: A,D


NEW QUESTION # 34
Where can you use the BCV report in SAP PPM?
NOTE: There are 3 correct answers to this question.

  • A. Bucket
  • B. Scoring model
  • C. Item
  • D. Metrics
  • E. Review

Answer: A,C,E


NEW QUESTION # 35
You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question

  • A. Update the capacity requirements from the roll-up of task requirements
  • B. Copy values from resource assignments
  • C. Enter the vales manually
  • D. Apply a distribution rule
  • E. Use a distribution function

Answer: A,C,E


NEW QUESTION # 36
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required?
NOTE: There are 2 correct answers to this question.

  • A. Categories
  • B. Cost element groups
  • C. Views
  • D. Value types

Answer: A,C


NEW QUESTION # 37
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?

  • A. Enable the split of financial values for the item type.
    * Assign the item to two bucket of the classification hierarchy
    * Maintain factors to split financial planning of the item
  • B. Enable the split of financial values for the item type
    * Assign the item to two bucket of the portfolio
    * Maintain factors to split financial planning of the item
  • C. Enable financial planning for multiple buckets
    * Assign additional buckets in financial planning
    * Maintain factors to split financial planning of the item.
  • D. Enable process change for multiple buckets.
    * Start process change to reassign the item two buckets
    * Maintain factors to split financial planning of the item

Answer: A


NEW QUESTION # 38
When is Bottom-up scheduling mandatory?

  • A. When constraints are used
  • B. When summary tasks are used
  • C. When actual time are recorded
  • D. When parallel phasing is used

Answer: B


NEW QUESTION # 39
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?

  • A. Portfolio dashboard
  • B. Business Context Viewer (BCV)
  • C. Evaluation
  • D. BI report

Answer: B


NEW QUESTION # 40
In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question

  • A. Project phase and WBS element
  • B. Project task and network activity
  • C. Milestone task and WBS element
  • D. Portfolio item and Project System project definition

Answer: A,D


NEW QUESTION # 41
......